Optimising wastewater operations: strategic pump upgrades in Alexandria
Growing population, rising demands: Alexandria's wastewater treatment infrastructure was reaching its limits. Learn how KSB mastered the challenges of a complex plant upgrade with innovative technology, innovative installation techniques and customer-focused service to transform Alexandria's treatment plant into a future-ready facility that is already planning the next expansion phase.
Growing population, rising demands: Alexandria's wastewater treatment infrastructure was reaching its limits. Learn how KSB mastered the challenges of a complex plant upgrade with innovative technology, innovative installation techniques and customer-focused service to transform Alexandria's treatment plant into a future-ready facility that is already planning the next expansion phase.
The project:
New intake pumps for Alexandria West Wastewater Plant
Basin of the Alexandria West Wastewater Treatment Plant
(image by Alexandria Water Company).
The client:
Alexandria Sanitary Drainage Company (ASDC)
The challenge:
Tailored approach for heavyweight pump integration
From German manufacturing to Egyptian installation

Side view of the upgraded pumping station with the Sewatec SPN fully supported by the new concrete foundation. The casing’s ring foot flange design provides flexibility of installation.
- Item 1
- Item 2
- Item 3
The solution:
Success story: Increased capacity and future expansion plans
Data | Facts | Figures
Sewatec SPN 900-1100 / G1 – VGW pumps
Delivery time ~ nine months
Installation, start-up and commissioning on-site additional six months
Used products
Sewatec
Volute casing pump for horizontal or vertical installation, with various next-generation impeller types, discharge flange to DIN and ANSI standards. Explosion-proof version available.